Project Description

The new cable stayed bridge, which will pass over the tip of Ada Ciganlija island, carries six traffic lanes and a double track light rail line as well as two pedestrian/cycling lanes. The bridge is a 6 span, continuous superstructure with an overall length of 929 meters and deck width of 45.04 m. The main support system is a single pylon asymmetric cable stayed structure. The pylon is 200 meters high.

In the category of SINGLE-pylon cable-stayed bridges, with its 376 m main span and deck width of 45 m together with the 200 m pylon, Sava bridge is the largest asymmetric cable-stayed bridge being constructed in the world at this present time, with almost 16.935 m2 of main span handing on ONE pylon.

With a main span of 376 m, the bridge over river Sava shall rank in the top 10 list of long span cable-stayed bridges constructed in Europe.

Sika Solutions

The Preliminary Design was completed by Ponting Maribor, DDC Ljubljana & CPV Novi Sad in 2006, as a first-awarded concept design proposal on international competition in 2004. The bridge is to be constructed using a Design-Build approach, with the detailed design to be completed by the contractor ‘Porr Technobau und Umwelt AG’. The contract will be administered under the FIDIC Conditions of Contract for Plan and Design Build, (First Edition, 1999).

Sika Products

In addition the following Sika products were used in the project

  • Sika® ViscoCrete®-3077
  • Plastiment® 20 R
  • Sika Antisol® S
  • Rugasol®-2 W
  • Sika® Betonloser
  • SikaTop®-122 SP
  • SikaRefit®
  • SikaLatex® Emulsion
  • SikaCor® EG System
  • Sikagard®-177
  • Sika® Permacor® 3326 EG-H
  • Sikadur®-42
  • Sikadur®-31
  • Sikadur®-Combiflex® Plus
  • SikaSwell®-P-2507-H
  • Sika®-4a
  • Sikadur®-52 Injection
  • Sikadur®-501

Check out more information about Sika products in the Serbian market